I-15; Juab County Line to Sevier River
Company
Hales Sand & Gravel
Project Type
Highway
Location
Central Utah
Project Name:聽 I-15 Juab County Line to Sevier River
Owner:聽 Utah Department of Transportation
General Contractor:聽 Hales Sand & Gravel
Start Date:聽 3/20
Completion Date:聽 10/20
Subcontractors or Key Contractors:聽 Premier Striping, Carlisle Excavation, Antigo Construction, B & K Construction, Straight Stripe Painting.
Materials Used and Quantities:
- 陆鈥 HMA 65,671 tons
- 3/8鈥 HMA 2,442 tons
- 陆鈥 SMA 22,519 tons
- Granular Barrow 35,740 tons
- UBC 28,160 tons